Autumn   Winter   Spring   Summer
Work programme   21 March – 20 June   21 June- 23 September   24 September – 21 December   22 December -20 March
Aeration /Seeding of Heretaunga Greens   30th March – 3rd April Heretaunga greens – Hollow tine core using 18mm tine.   6th July – 10th July Heretaunga greens – Spike verti- drain.   7th September – 11th September Heretaunga greens – Hollow tine core using 4mm tine.    
        7th September – 11th September Heretaunga greens – Hollow tine core using 4mm tine.   16th November – 20th November Heretaunga greens – Hollow tine core using 4mm tines.    
    Heretaunga greens –  disc seed Creeping bent  grass            
Terrace course greens / range tee   9th March – 13th March Terrace Course greens / Range tee – Hollow tine core using 18 mm tine.   8th June – 11th June Terrace Course greens / Range tee – Spike verti-drain.   28th September – 30th September Terrace course greens / Range tee – Hollow tine core using 13mm tines    
Heretaunga Greens Collars   April Remove and replace turf with Brown top.            
    Aeration treatments same as Heretaunga greens plan.            
Heretaunga Green Approaches   Aeration treatments same as Terrace course greens  / Range tee plan.            
                 
Heretaunga Tees   16th March – 20th March Heretaunga tees – Hollow tine core using 18mm tine.   31st August – 4th September Heretaunga tees – Hollow tine core using 18mm tines.   23rd November – 27th November – Hollow tine core using 13mm tines.    
All Fairwyas   6th – 7th March Scarifying of fairways.            
    4th May – 1st June Verti drain all fairways.   3rd August – 10th August Heretaunga fairways spray fairways with Amitrol. (One application)        
        14th September – 28th September Heretaunga fairways disc seed fairways with Brown top at 2 g/m2 (spot treatment).        
Heretaunga 1st cut of rough   April  Heretaunga  course spray 25 hectares of our rough with Haloxyfop.             
    May Heretaunga course – Drill seed two varieties of fescue   September Heretaunga course – Haloxyfop spraying.to remove?        
Course Paths               February / March Path ends to be cored and over seeded with Cynodon.
Enviromental / Long grass areas / Repairan Margins               January / February – Spot spray weeds
                February – Spot spray with Haloxyfop
                Feb / March – Trim seed heads off with Steiner mower / weed eaters.
Tree felling    On going as conditions allow.            
Bunker Renovations   Following the very successful project completed on the 15th hole bunkers on 4, 15 and 16 will be renovated using porous concrete with new sand added. – We will recycle the old sand and use it in the Terrace course bunkers.